South Okanagan landfill copes with mounting debt

Reduced hours of operation and increased tipping fees are among the options being considered as the local landfill’s operator tries to bury a mounting financial deficit.

Total revenue from the Campbell Mountain landfill is expected to come in $400,000 under its budget projection of $2.8 million this year, a gap expected to grow to $700,000 next year if no action is taken.

The board of the Regional District of Okanagan-Similkameen, which operates the landfill, was last week told it should consider raising tipping fees and reducing hours of operation to better balance revenues and expenses. On Thursday afternoon, the board was expected to consider some hard numbers at its first budget session of the year.

Increasing tipping fees from $65 a tonne to $80 a tonne would raise an additional $368,000 annually, according to an analysis prepared by finance director Warren Everton. The $80 level is the break-even cost suggested by a report prepared last year that examined the site’s life expectancy. Everton also estimated that closing the site on Sundays year-round, rather than from December to February only, could save the RDOS an additional $110,000 annually.

When public works manager Doug French last week pitched that idea to an RDOS board committee, he noted reduced hours would likely lead to longer lineups at the scale house and could have other ramifications, such as an increased volume of waste being left out for residential curbside pickup.

The budget analysis contained several other accounting measures that would net an additional $170,000 a year and trim the landfill’s projected operating deficit to $52,000, which could be covered by a “small taxation component.”

According to French’s report last week, the landfill’s finances have taken a beating as the amount of revenue-generating waste entering the site has decreased and the amount of recyclable material, most of which can’t be sold for profit, has increased.

 

In 2011, the site received 25,000 tonnes of waste material, down from 47,000 tonnes in 2003, the report explained. Meanwhile, the weight of recyclable material collected at the landfill increased from 4,900 tonnes in 2003 to 8,600 tonnes in 2011.

 

 

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

Security stepped up in B.C. after attacks in Ottawa
 
UPDATE: B.C. legislature on alert before Ottawa shooting
 
Albas off to Ottawa
Election 2014: Penticton sees record number of candidates
 
Peach City Radio faces big challenge
 
Soldier killed in Parliament Hill siege
Biomass identified as best option for Nelson energy system
 
Year in Review - July 2011
 
Prince Rupert SPCA projecting $175,000 deficit

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 22 edition online now. Browse the archives.