Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Man allegedly wielding knife at Kelowna Superstore arrested

The 29-year-old Kelowna man has been released on strict conditions for a future court date

Ryga Arts Festival to include live events

Arts festival in Summerland will feature live and online performances

City of Penticton seeking input of future transportation plans

City planners aim to balance traditional and modern modes of transport in future

South Okanagan sees increase in real estate activity

More single family homes sold at higher prices when compared with a year ago

Penticton Peach Fest headliners moved to 2021

Artists include Glass Tiger, Simply Queen, Jess Moskaluke and Honeymoon Suite

B.C. would not send students back to school if there was ‘overwhelming risk’: Horgan

Plan has left many parents across the province worried about their children’s safety

VIDEO: A B.C business used robots to bring down concrete walls

Walco Industries is the only firm on Vancouver Island to use specialized robots for hydro-demolition

As CERB winds down, labour group asks Liberals to rethink EI

The government estimates four million people will be moved onto EI after CERB ends

Highway 3 closed south of Princeton after vehicle incident

There is currently no detour, Drive BC stated, but crews are on scene

North Okanagan man chains himself to tree in protest of construction

Crews began work clearing space for a new facility Thursday, Aug. 6

Search crews en route to vehicle over Coquihalla Highway embankment

Incident on northbound side of highway near Great Bear Snowshed: SAR

Fire causes significant damage to West Kelowna home

The fire was first reported at 10:30 a.m. on Aug. 6.

North Okanagan police search for owner of lost iPhone

Concerned citizen turns phone into RCMP

Most Read