UPDATE: Parties square off over Site C delays

Rushed report unable to determine if dam on $8.8 billion budget

The NDP government’s deadline to deliver a preliminary report on B.C. Hydro’s Site C dam project didn’t allow time to determine if the most expensive construction job in B.C. history is on budget.

Energy Minister Michelle Mungall faced questions in the legislature Thursday about the government-ordered review with a Sept. 20 deadline for a preliminary report, an extra set of public hearings and a final report by Nov. 1. That report will form the basis for the government’s decision on whether to temporarily stop work on the project, proceed with construction or halt the project and remediate the site on the Peace River near Fort St. John.

Peace River South MLA Mike Bernier called on Mungall to assure the 2,600 workers on the project that their jobs are safe as winter approaches. Mungall fired back that the expert review by the B.C. Utilities Commission is a step the B.C. Liberals refused to take, and that is why it is being taken now.

The BCUC released the report ordered by Premier John Horgan’s cabinet late Wednesday evening, hours before a midnight deadline. It leaves more questions than answers as the BCUC proceeds to a new round of province-wide public meetings it was also ordered to hold.

The BCUC review panel concluded it didn’t have enough information to answer questions put to it by the government, on an $8.8 billion construction project that has been underway for two years.

“The panel is concerned that the amount spent on the project as of June 30, 2017, $1.8 billion, might not accurately represent the spending that should have happened on the project activities to date,” the report states.


Like us on Facebook and follow us on Twitter.

Just Posted

Shinedown to debut new music in Penticton

Penticton concert-goers will be the first to hear a new song from Shinedown’s sixth album

Mudslide at South Okanagan golf course

A mudslide occurred at Fairview Mountain Golf Club in Oliver

SD67 fills 2-year gap in Aboriginal education administration

District also announces shuffling of school admin, with Princess Maggie VP heading to Pen High

Prescribed burns to close Penticton channel path

The burns will close the path from 6 a.m. to 9 p.m. Wednesday and Thursday next week

What’s happening

Find out which events are taking place in the Okanagan and Shuswap this weekend

Canucks sing the Blues as they fall to St. Louis 4-1

Berglund nets two, including the game-winner, to lift St. Louis over Vancouver

Calving season brings hope for Cariboo ranchers

Still a lot of work ahead to recover from the wildfires

Canada’s Kaetlyn Osmond wins figure skating world title

The 22-year-old fwon the women’s singles crown with her Black Swan routine

B.C. pooches celebrate National Puppy Day

Check out some of the submissions from around B.C. for National Puppy Day 2018

Similkameen residents face long wait for bus solution

Scheduling key for Similkameen bus riders in proposed B.C. Transit Penticton to Kelowna expansion

Rainstorm causes road flooding in Naramata and Okanagan Falls

Flood assessments conducted in Okanagan Falls and Naramata

Photos: Salmon Arm celebrates Paralympic champion Natalie Wilkie

Hometown hero welcomed home with parade, recognition ceremony at city hall

Most Read