Court allows appeal on pipeline certificate, says B.C. needs to reconsider

Province’s approval of certificate was based on quashed original report from National Energy Board

Pipeline pipes are seen at a Trans Mountain facility near Hope, B.C., Thursday, Aug. 22, 2019. (Jonathan Hayward / The Canadian Press)

The British Columbia government has been ordered by the province’s highest court to reconsider its environmental assessment certificate allowing the expansion of the Trans Mountain pipeline.

In challenges by the Squamish Nation and the City of Vancouver, the B.C. Court of Appeal ruled the province’s approval of the certificate was based on the original report from the National Energy Board, which was later quashed by the Federal Court of Appeal.

After the National Energy Board reviewed the project for a second time, the federal government approved the pipeline expansion again.

READ MORE: Thousands of landowners on Trans Mountain pipeline route have yet to grant access

The Appeal Court says in its decision released today that in light of changes to the original report of the energy board when it reconsidered the project, provincial approval also needs to be reconsidered.

B.C.’s former Liberal government approved the expansion with 37 conditions, while relying on an agreement with the energy board that would stand for a provincial environmental assessment.

The three-judge panel said in its unanimous decision that through no fault of the provincial government, what is now Canada’s environmental assessment of the pipeline was not the same assessment used when B.C. approved its certificate.

The court dismissed other claims by the city and the Squamish Nation including that the province failed to sufficiently consult with Indigenous groups.

The Federal Court of Appeal agreed earlier this month to hear arguments from First Nations that argue they were improperly consulted before the federal government approved the pipeline expansion for the second time.

The City of Vancouver says in a statement that it’s pleased with the court’s decision. One of the reasons the city pursued the case was the Federal Court of Appeal’s decision that overturning Ottawa’s approval of the project, which led the energy board to reconsider the project and issue a new report.

“The City remains of the view that the Trans Mountain Pipeline project would have significant environmental impacts, including the unacceptable risk of oil spills and increased greenhouse gas emission related to the project at a time when the world needs to reduce emissions,” it says.

Environment Minister George Heyman was not immediately available for comment. Representatives from Trans Mountain and the Squamish Nation could not immediately be reached for comment.

The project would triple the capacity of an existing pipeline from Alberta’s oilpatch to a terminal in Burnaby, B.C.

The federal government bought the existing pipeline and the unfinished expansion work for $4.5 billion last year, promising to get it past the political opposition that had scared off Kinder Morgan Canada from proceeding.

The Canadian Press

READ MORE: Pembina CEO says ‘noise’ makes Trans Mountain pipeline bid unlikely

Like us on Facebook and follow us on Twitter

Just Posted

Penticton council approves 2.9 per cent tax increase in 2020 budget

Council will vote in the new budget at an upcoming meeting in the new year

Penticton resident allegedly has rear car tires stolen

The resident woke up today to find their back tires missing and their car on blocks

Funding sought for family of 15-year-old Summerland girl with cancer

Treatment will involve two weeks in hospital, followed by eight to 10 weeks recovery at home

I’m Just Saying: Our society needs a re-sex education lesson

Jordyn Thomson is a reporter with the Western News

PIB to host new by-election after successful appeal of 2017 results

On Dec. 13, the membership voted to host a new by-election

VIDEO: More air-passenger rights go into effect this weekend

The first set of passenger rights arrived in mid-July in Canada

Best in business: North-Okanagan Shuswap companies named top 10 semi-finalists

Small businesses from Vernon, Kelowna, West Kelowna, Salmon Arm to compete for top spot

Sagmoen’s lawyer argues ‘abuse of power’ in police search

The trial of Curtis Sagmoen continued at the Vernon Law Courts on Friday

Swoop airlines adds three destinations in 2020 – Victoria, Kamloops, San Diego

Low-fair subsidiary of WestJet Airlines brings new destinations in April 2020

Aid a priority for idled Vancouver Island loggers, John Horgan says

Steelworkers, Western Forest Products returning to mediation

Navigating ‘fever phobia’: B.C. doctor gives tips on when a sick kid should get to the ER

Any temperature above 38 C is considered a fever, but not all cases warrant a trip to the hospital

Woman struck, dog killed after collision on Highway 97

Speed is not believed to be a factor and alcohol has been ruled out

Transportation Safety Board finishes work at B.C. plane crash site, investigation continues

Transport Canada provides information bulletin, family of victim releases statement

Trudeau sets 2025 deadline to remove B.C. fish farms

Foes heartened by plan to transition aquaculture found in Fisheries minister mandate letter

Most Read