Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Controlled burns taking place across Okanagan

That smoke you see on Okanagan hillsides is supposed to be there

Penticton students prepare for this year’s 10,000 Tonight

On Nov. 29 students will canvass neighbourhoods collecting food items for the Salvation Army

Restorative Justice helps communities heal

This week is Restorative Justice Week. Several workshops are planned throughout the region.

Reducing the risk of wildfire in Kaleden

Kaleden community organizing forum to plan for future wildfires

Dogs in the classroom

Therapy dogs help young students learn in the Okanagan

Drones used in search for clues about missing women

A volunteer search party was supported by professional drone operators

B.C. sports groups to address child sex abuse in sports

viaSport is organizing a full day of education in association with Canadian Centre for Child Protection and the Coaching Association of Canada.

Report sets exercise guidelines for young kids, including ‘tummy time’ for babies

Kids aged one to four should get at least three hours of physical activity throughout the day

Stampeders return to Grey Cup with 32-28 win over Edmonton Eskimos

The Stampeders will face the Toronto Argonauts next Sunday in Ottawa for the title

Traxxas Monster Truck Tour to roll into Kelowna

Monster Trucks at Prospera Place on Jan. 13-14, 2018.

Nebraska approves TransCanada’s Keystone XL pipeline

Nebraska’s Public Service Commission approved TransCanada’s Keystone XL route in a close vote

B.C. VIEWS: China a better partner than U.S.

B.C. is slowly winning the softwood lumber war

Forecast calls for a snowy Canadian winter

Canadians told to brace for a ‘classic’ Canadian winter with lots of snow

Queen Elizabeth II, Prince Philip celebrate 70th anniversary

The Queen and The Duke of Edinburgh are celebrating their platinum wedding anniversary

Most Read