Grizzly Excavating awarded $10.5M contract to build Penticton Point Intersection

Work set to begin along Greenwood Drive on May 2
32510502_web1_210414-PWN-SeniorsHousing_1
The old Shielings Motel was demolished more than two years ago in 2021 for the Point Intersection project. All of the renters at the site were forced to find other arrangements. The city is still planning to have affordable seniors housing on the site. (Brennan Phillips - Penticton Western News)

The City has awarded the $10.5 million construction contract for the Point Intersection and associated work to Grizzly Excavating, with work set to begin along Greenwood Drive on Tuesday, May 2.

Work is anticipated to be complete by fall 2024 and will include the last phase of the bike lane down South Main.

“This work is being done to address congestion in the area, which will only increase with the anticipated growth that is expected in the upper Wiltse area,” said Mayor Julius Bloomfield. “These upgrades will also improve the safety for all road users, including cyclists and pedestrians, and add some much-needed greenspace to the area.”

Despite a budget that shot up by $3 million, Penticton gave the green light to proceed with the intersection project.

READ MORE: Green light for $3M over budget Galt and Kinney project

The sequencing of work for the project will be completed to minimize traffic impacts as much as possible, as follows:

• A sidewalk on Greenwood Drive will be installed between Green Avenue East and Dartmouth Drive, and along Dartmouth Drive to Pineview Road starting in May. The road will be open to local traffic.

• Work will begin on the reconstruction of Galt Avenue later this spring.

• Work on Pineview Road and South Main Street will begin in the summer.

• Asphalt and paving work along Main Street and Warren Avenue are scheduled for the fall.

• A roundabout will be constructed at the Galt Avenue/South Main Street/Pineview Road intersection, also starting in the fall.

Skaha Lake Road repaving, and installation of a traffic signal at Galt Avenue, will start early next year.

Once the signalized intersection and roundabout are complete, Kinney Avenue will be closed to vehicle traffic and converted to green space and the pedestrian/bike connection.

At the same time, the remaining $1.5 million section of the Lake-to-Lake Route will be installed, connecting the existing work at Atkinson Street down South Main Street to just south of the roundabout. The final design of the new bike lane section will be released soon, said the city.

READ MORE: Mistaken vote by Penticton councillor gives life to bike lane’s final phase

“Given the large scope of this project, construction is expected to be completed late next year, and is anticipated to cause significant disruption. We will work diligently to notify neighbours and the community well in advance, and encourage all residents to stay informed by signing up for news updates from the City,” says Kristen Dixon, general manager of infrastructure.

Work will be conducted on weekdays between 7 a.m. and 10 p.m. and on weekends between the hours of 9 a.m. and 5 p.m., unless approved for required night work.

To report a typo, email: editor@pentictonwesternnews.com.

<>

Don’t miss a single story and get them delivered directly to your inbox. Sign up today for the Penticton Western News Newsletter.

<>

@PentictonNews
newstips@pentictonwesternnews.com

Like us on Facebook and follow us on Twitter.



Monique Tamminga

About the Author: Monique Tamminga

Monique brings 20 years of award-winning journalism experience to the role of editor at the Penticton Western News. Of those years, 17 were spent working as a senior reporter and acting editor with the Langley Advance Times.
Read more