Drone photo of Park Bridge completed in 2015 in Kicking Horse Canyon shows challenge of highway widening through the Rocky Mountains. (Ministry of Transportation)

Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

PHOTOS: Shinedown and Papa Roach light up Penticton’s SOEC

Asking Alexandria and Savage After Midnight opened the show on Oct. 16

How local candidates are using Facebook to advertise directly to you

Liberal campaign is the biggest spender on Facebook ads in South Okanangan–West Kootenay

Grab your Lederhosen, Penticton Oktoberfest is tomorrow!

The 10th annual event is hosted at the Penticton Lakeside Resort and kicks off Penticton Beer Week

South Okanagan’s first swim meet of the season

The Penticton KISU Swim Club is hosting its first meet of the season this weekend

Charles wows them at iconic South Okanagan venue

Blues musician Michael Charles played to a sold-out crowd at the Dream Café Saturday

VIDEO: First all-female spacewalk team makes history

NASA astronauts Christina Koch and Jessica Meir did work on International Space Station’s power grid

Shooters compete in Summerland

Seven youth participants take aim

B.C. public safety minister says cannabis edibles not in stores til January

Mike Farnworth says he wants regional issues considered when it comes to licensing

Greta Thunberg calls for climate action in Alberta, but doesn’t talk oilsands

Swedish teen was met with some oil and gas industry supporters who came in a truck convoy

RDOS cannabis production bylaw goes to public hearing

Hearing on micro cannabis production facilities will be held Nov. 21

Scheer denies spreading ‘misinformation’ in predicting unannounced Liberal taxes

Conservative leader had claimed that a potential NDP-Liberal coalition could lead to a hike in GST

Council asks to limit cruise ship visits to Victoria harbour

Mayor says motion is not meant to curtail current visits or limit local cruise industry expansion

Chilliwack man pleads guilty in crash that killed pregnant woman

Frank Tessman charged under Motor Vehicle Act for accident that killed Kelowna school teacher

Letter: Debate rules not followed

After watching some of the English language debate, and giving up after… Continue reading

Most Read